33
Total Applications
Obtaining water connection
Apply for Obtaining Water Connection for construction/operation/ miscellaneous purposes from the IDCO industrial estates. After receiving applications, after examining the requirements and comparing it with available benchmarks, recommend for issuing the connection.
Fields marked with ‘*’ are mandatory and should be filled in before submitting the form in GO SWIFT portal Leaving fields blank in the Form is not allowed. In case applicants wish not to enter data in a field, they can put “NA” if it is a text/description field or a “0”, if it is a numeric field. In case of errors, the form will show an error message. The applicant may correct the data and save the form again.
Applicants can attach documents in digital format as documentary evidences which the department will use for verification. Clicking on the choose button will let them select the document to be uploaded. Before submitting the document, they needs to ensure that all the information furnished by them is satisfactory and correct to the best of their knowledge and understanding. After checking that the information furnished in all the fields are in order, they can submit the application by clicking on the ‘Submit’ button.
After the form is successfully submitted, applicants can pay the required fees on online mode only. The processing fees required to be paid is as follows:
Fee Details
|
Processing amount to be paid
|
|
|
Processing Fees
|
INR 6,000/- excluding GST
|
IT corpus Fund
|
INR 120/-
|
Upon payment the applicant will receive an SMS & Email notification with the application number from the single window portal. After receiving processing fee, IDCO will generate a separate demand note
Checklist of Documents
The applicant will need to attach the following documents with the application:
1. Plumber Details: The Name, address and license number of plumbing contractor
2. Sump/ Tank Details: The type and size (volumetric) of water storing arrangement
Timeline
Water Connection application is processed and disposed within 30 working days from the date of receipt of application. The department can however, raise queries on the application within 7 working days of receipt of application.